{"attribution":"Figures as published by the source named in each record. Compiled, cleaned, flagged and joined by Kanakku. Credit both.","changes":[],"first_seen_on":"2026-09-30","flags":[{"cleared_on":null,"raised_on":"2026-09-30","rule_version":2,"status":"open","type":"overdue","value":{"days_overdue":367,"scheduled_end":"2025-09-30","status":"Inprogress"},"work":"Peruman bridge"}],"license":"CC-BY-4.0","license_url":"https://creativecommons.org/licenses/by/4.0/","missing_since":null,"project":{"code":"PWD001-38-01","constituencies":[{"mla_name":null,"mla_name_ml":null,"name":"Kunnathur","name_ml":"കുന്നത്തൂർ"}],"department":"Public Works Department","district":"Kollam","districts":["Kollam"],"estimate_shared_by":0,"estimated_amount":null,"executing_agency":"KRFB","expenditure":null,"group_expenditure":null,"sector":null,"sites":[],"status":null,"sub_project_code":null,"title":"68 Bridges","works":[{"as_amount":600000000,"contract_amount":479934593,"contractor":"M/s.CherianVarkeyConstructionCoPvt.Ltd","financial_pct":61.65228692,"fs_amount":523713082,"lat":8.971367840552313,"lng":76.6096307657141,"loa_amount":null,"paid_amount":295890652,"paid_contractor":276489796,"physical_pct":77.86193377,"progress_note":"All 80 out of 80 piles are completed. Also 12 out of 16 nos of pile cap, 8 out of 10 sets of piers and 8 out of 10 pier caps completed, Pier wall (Abutment) 1 out of 1,girder casting completed in perumon side and slab work in progress except centre sp","road_name":"Peruman bridge","scheduled_end":"2025-09-30","scheduled_start":"2020-10-30","spv":"KRFB","status":"Inprogress","tender_amount":476323456,"ts_amount":492010272}]},"source":{"retrieved_at":"2026-09-30T11:10:07.786Z","sha256":"04a00101b9212117e081e445510a368fa8396ac84f209ff4f843707428dd17ef","snapshot":"/snapshot/1","url":"https://gis.kiifb.org/"}}