Who must repair it
When PWD finishes a road or a building, the contractor stays liable for a set period to repair defects at their own cost. These are the works inside that period, as PWD lists them.
Works under liability now
161
165 works on the list in all
Liability ends within 90 days
35
After that, repairs fall to the public purse.
Contractors
64
Names as PWD publishes them.
If you see a defect: If a work on this list fails inside its period, PWD can make the contractor put it right. Report it to PWD; its own list names the office responsible for each work. PWD's list
The district is that of the PWD office handling the work; some offices also look after works in neighbouring districts.
- 2020-21 Providing BM and BC to Cherukunnam Vettiyar road 5/400 to 8/400Roads · Roads Sub Division MavelikkaraK. Sasidharan Prop Metaquard EngineersLiable from 04-10-2023 until 04-10-2026
- 2020-21 Providing BM and BC to Cherukunnam Vettiyar road 5/400 to 8/400Roads · Roads Sub Division MavelikkaraK. Sasidharan Prop Metaquard EngineersLiable from 08-10-2023 until 08-10-2026
- 2020-21 Providing BM and BC to Cherukunnam Vettiyar road 5/400 to 8/400Roads · Roads Sub Division MavelikkaraK. Sasidharan Prop Metaquard EngineersLiable from 09-10-2023 until 09-10-2026
- 2020-21 Providing BM and BC to Cherukunnam Vettiyar road 5/400 to 8/400Roads · Roads Sub Division MavelikkaraK. Sasidharan Prop Metaquard EngineersLiable from 10-10-2023 until 10-10-2026
- Budget work 2021-22-Improvements to Arattuvazhi Palli - Bypass roadRoads · Roads Sub Division AlappuzhaThaslim ALiable from 06-11-2023 until 06-11-2026
- SLTF-FDR 2022-23 Providing drainage facilities to Block Headquarters - Cheruthanakadavu road near Ch. 0/000-FDR 2022-23 Providing drainage facilities to Block Headquarters - Cheruthanakadavu road near Ch. 0/000Roads · Roads Sub Division AlappuzhaMuhammed AfsalLiable from 09-11-2023 until 09-11-2026
- SLTF-SLTF 2020-21 Construction of Box culvert across Madayanthodu in SL Puram road-work-General Civil Work-1Roads · Roads Sub Division AlappuzhaJ. ManzoorLiable from 09-11-2023 until 09-11-2026
- Budget work 2021-22-Improvements to Arattuvazhi Palli - Bypass roadRoads · Roads Sub Division AlappuzhaThaslim ALiable from 11-11-2023 until 11-11-2026
- SLTF-SLTF 2020-21 Construction of Box culvert across Madayanthodu in SL Puram road-work-General Civil Work-1Roads · Roads Sub Division AlappuzhaJ. ManzoorLiable from 11-11-2023 until 11-11-2026
- SLTF-FDR 2022-23 Providing drainage facilities to Block Headquarters - Cheruthanakadavu road near Ch. 0/000-FDR 2022-23 Providing drainage facilities to Block Headquarters - Cheruthanakadavu road near Ch. 0/000Roads · Roads Sub Division AlappuzhaMuhammed AfsalLiable from 13-11-2023 until 13-11-2026
- SLTF-SLTF 2020-21 Construction of Box culvert across Madayanthodu in SL Puram road-work-General Civil Work-1Roads · Roads Sub Division AlappuzhaJ. ManzoorLiable from 13-11-2023 until 13-11-2026
- SLTF-FDR 2022-23 Providing drainage facilities to Block Headquarters - Cheruthanakadavu road near Ch. 0/000-FDR 2022-23 Providing drainage facilities to Block Headquarters - Cheruthanakadavu road near Ch. 0/000Roads · Roads Sub Division AlappuzhaMuhammed AfsalLiable from 14-11-2023 until 14-11-2026
- Budget work 2021-22-Improvements to Arattuvazhi Palli - Bypass roadRoads · Roads Sub Division AlappuzhaThaslim ALiable from 16-11-2023 until 16-11-2026
- SLTF-FDR 2022-23 Providing drainage facilities to Block Headquarters - Cheruthanakadavu road near Ch. 0/000-FDR 2022-23 Providing drainage facilities to Block Headquarters - Cheruthanakadavu road near Ch. 0/000Roads · Roads Sub Division AlappuzhaMuhammed AfsalLiable from 19-11-2023 until 19-11-2026
- Budget work 2021-22 (KUTTITTU PARAMBU-KEVELI TODU)Road-Improvements to KUTTITTU PARAMBU-KEVELI TODU Road at Mannanchery PanchayathuRoads · Roads Sub Division AlappuzhaA Mohammed IsmailLiable from 20-11-2023 until 20-11-2026
- Budget work 2019-20 Chengannur Flood Relief - Reconstruction of various roads in Chengannur LAC-In Pandanad GramapanchayathRoads · Roads Sub Division ChengannurA G Rajmohan NairLiable from 22-11-2023 until 22-11-2026
- Budget work 2021-22 (KUTTITTU PARAMBU-KEVELI TODU)Road-Improvements to KUTTITTU PARAMBU-KEVELI TODU Road at Mannanchery PanchayathuRoads · Roads Sub Division AlappuzhaA Mohammed IsmailLiable from 23-11-2023 until 23-11-2026
- Budget work 2021-22-Improvements to Arattuvazhi Palli - Bypass roadRoads · Roads Sub Division AlappuzhaThaslim ALiable from 23-11-2023 until 23-11-2026
- SLTF-SLTF 2020-21 Construction of Box culvert across Madayanthodu in SL Puram road-work-General Civil Work-1Roads · Roads Sub Division AlappuzhaJ. ManzoorLiable from 23-11-2023 until 23-11-2026
- Budget work 2021-22 (KUTTITTU PARAMBU-KEVELI TODU)Road-Improvements to KUTTITTU PARAMBU-KEVELI TODU Road at Mannanchery PanchayathuRoads · Roads Sub Division AlappuzhaA Mohammed IsmailLiable from 29-11-2023 until 29-11-2026
- Budget work 2021-22-Improvements to Arattuvazhi Palli - Bypass roadRoads · Roads Sub Division AlappuzhaThaslim ALiable from 30-11-2023 until 30-11-2026
- SLTF-FDR 2022-23 Providing drainage facilities to Block Headquarters - Cheruthanakadavu road near Ch. 0/000-FDR 2022-23 Providing drainage facilities to Block Headquarters - Cheruthanakadavu road near Ch. 0/000Roads · Roads Sub Division AlappuzhaMuhammed AfsalLiable from 11-12-2023 until 11-12-2026
- Reconstruction of damaged drain and providing interlock tiles on both sides of Alappuzha Maduraroad between ch 2/100 and 2/500Roads · Roads Sub Division AlappuzhaNizar PMLiable from 24-12-2021 until 24-12-2026Agreed amount ₹46.74 lakh · ₹46,74,020
- SLTF-SLTF 2020-21 Construction of Box culvert across Madayanthodu in SL Puram road-work-General Civil Work-1Roads · Roads Sub Division AlappuzhaJ. ManzoorLiable from 27-12-2023 until 27-12-2026
- Budget work 2019-20 -Chengannur Flood Relief -Reconstruction of various roads in Chengannur LAC-In Venmony Grama panchayathRoads · Roads Sub Division ChengannurM/S Valayanattu Hiring And Construction CompanyLiable from 30-12-2023 until 30-12-2026
- Budget work 2019-20 Chengannur Flood Relief - Reconstruction of various roads in Chengannur LAC-In Pandanad GramapanchayathRoads · Roads Sub Division ChengannurA G Rajmohan NairLiable from 30-12-2023 until 30-12-2026
- Budget work 2019-20-Budget work 2019-20 - Chengannur Flood Relief Reconstruction of Various roads in Chengannur LAC in Chengannur Municipality.Roads · Roads Sub Division ChengannurJojy ThomasLiable from 18-01-2024 until 18-01-2027
- Budget work 2021-22-Improvements to Arattuvazhi Malikamukku roadRoads · Roads Sub Division AlappuzhaShan P ThomasLiable from 20-01-2024 until 20-01-2027
- Budget work 2021-22-Improvements to Arattuvazhi Malikamukku roadRoads · Roads Sub Division AlappuzhaShan P ThomasLiable from 24-01-2024 until 24-01-2027
- Budget work 2021-22-Improvements to Arattuvazhi Malikamukku roadRoads · Roads Sub Division AlappuzhaShan P ThomasLiable from 25-01-2024 until 25-01-2027
- Budget work 2021-22-Improvements to Arattuvazhi Malikamukku roadRoads · Roads Sub Division AlappuzhaShan P ThomasLiable from 26-01-2024 until 26-01-2027
- Budget work 2021-22-Improvements to Arattuvazhi Malikamukku roadRoads · Roads Sub Division AlappuzhaShan P ThomasLiable from 27-01-2024 until 27-01-2027
- Budget work 2021-22-Improvements to Arattuvazhi Malikamukku roadRoads · Roads Sub Division AlappuzhaShan P ThomasLiable from 29-01-2024 until 29-01-2027
- Budget work 2019-20-Budget work 2019-20 - Chengannur Flood Relief Reconstruction of Various roads in Chengannur LAC in Chengannur Municipality.Roads · Roads Sub Division ChengannurJojy ThomasLiable from 30-01-2024 until 30-01-2027
- Budget work 2019-20-Budget work 2019-20 - Chengannur Flood Relief Reconstruction of Various roads in Chengannur LAC in Chengannur Municipality.Roads · Roads Sub Division ChengannurJojy ThomasLiable from 09-02-2024 until 09-02-2027
- DEPOSIT-RESTORATION-Restoration work of Ravi Karunakaran Road 2nd bit due to KWA Amruth New Pipe LayingRoads · Roads Sub Division AlappuzhaNizar P MLiable from 28-03-2023 until 28-03-2028
- SLTF 2020-21 Providing drain, covering slab and interlock to water logged area in Perissery- Kurishummoodu- Grace theatre road at Ch 0/000 to 1/890 and Reconstruction of culvert at Ch 0/780Roads · Roads Sub Division ChengannurBabu MPLiable from 23-05-2023 until 23-05-2028
- SLTF 2020-21 Reconstruction of culvert in Perissery - Kurishumoode - Grace theatre road at ch 0/400.Roads · Roads Sub Division ChengannurAneesh SachariaLiable from 23-05-2023 until 23-05-2028
- DEPOSIT-RESTORATION WORK AMRUT-Restoration to KSRTC Chungam road due to road cut by KWA for AMRUT ProjectRoads · Roads Sub Division AlappuzhaNishad T SheriefLiable from 30-06-2023 until 30-06-2028
- LAC-ADS-MLA ADS 2021-22 Improvements of Haripad KSRTC depot- - construction of yard and road -DPR Preparation WorkRoads · Roads Sub Division AlappuzhaAbdul Javad.mLiable from 15-07-2023 until 15-07-2028
- SR Works 2022-23-Providing Drainage facilities at Pattamukku Junction in SL Puram RoadRoads · Roads Sub Division AlappuzhaShahir IbrahimLiable from 20-01-2024 until 20-01-2029
- DEPOSIT-RESTORATION WORK AMRUT-Restoration to KSRTC Chungam road due to road cut by KWA for AMRUT ProjectRoads · Roads Sub Division AlappuzhaNishad T SheriefLiable from 22-01-2024 until 22-01-2029
- DEPOSIT-RESTORATION WORK AMRUT-Restoration to KSRTC Chungam road due to road cut by KWA for AMRUT ProjectRoads · Roads Sub Division AlappuzhaNishad T SheriefLiable from 24-01-2024 until 24-01-2029
- SR Works 2022-23-Providing Drainage facilities at Pattamukku Junction in SL Puram RoadRoads · Roads Sub Division AlappuzhaShahir IbrahimLiable from 24-01-2024 until 24-01-2029
- SR Works 2022-23-Providing Drainage facilities at Pattamukku Junction in SL Puram RoadRoads · Roads Sub Division AlappuzhaShahir IbrahimLiable from 29-01-2024 until 29-01-2029
- DEPOSIT-RESTORATION WORK AMRUT-Restoration to KSRTC Chungam road due to road cut by KWA for AMRUT ProjectRoads · Roads Sub Division AlappuzhaNishad T SheriefLiable from 31-01-2024 until 31-01-2029
- SR Works 2022-23-Providing Drainage facilities at Pattamukku Junction in SL Puram RoadRoads · Roads Sub Division AlappuzhaShahir IbrahimLiable from 04-02-2024 until 04-02-2029
- Budget Work 2019-20 Improvements by Providing DGBM &BC to West of mavelikkara temple to South of Kandiyoor temple Road from Ch 0/000 to 1/600Roads · Roads Sub Division MavelikkaraB Sree KumarLiable from 30-09-2023 until 30-09-2026
- Budget work 2019-20-Budget work 2019-20 - Chengannur Flood Relief Reconstruction of Various roads in Chengannur LAC in Chengannur Municipality.Roads · Roads Sub Division ChengannurJojy ThomasLiable from 30-09-2023 until 30-09-2026
Contractors with the most works
Counted by works now under liability. We treat different spellings of a name as one; two people with the same name may have been counted together.
Source
Source: the Kerala Public Works Department's DLP work list, which we read once a week. We do not keep or show the phone numbers printed on PWD's pages. The agreed amount sits in the code of PWD's page without being displayed there, and PWD has filled it in for only 1 of the 161 works now under liability.