Kanakkuമലയാളം
Public WorksApproved

Construction of Flyover at Sreekariyam in Thiruvananthapuram

Approved by KIIFB

₹168.68 crore

₹1,68,68,02,675

Paid so far

₹115.01 crore

₹1,15,00,54,336 · 68.2% of the amount approved

Works

5

₹115.01 crore paid across the works

KIIFB's figures do not agree here: its list says ₹1,68,68,02,675 was approved for the project, while the approvals of the works add up to ₹1,76,80,21,654. Both are shown as the source states them.

Works (5)

Land Acquisition for Sreekaryam Flyover

Work awarded
₹98.36 crorepaid
₹98.36 croreapproved

Utility Shifting - Kerala Water Authority

Work awarded
₹4 crorepaid
₹4 croreapproved

Utility Shifting - KSEB

Work awarded
₹2.58 crorepaid
₹2.58 croreapproved

Utility Shifting - BSNL

Work awarded
₹48.38 lakhpaid
₹48.38 lakhapproved

Construction of Flyover at Sreekaryam - Civil Works

Work awarded
₹9.58 crorepaid
₹71.38 croreapproved

Total of the works: ₹1,76,80,21,654 approved, ₹1,15,00,54,336 paid.

Details

Department
Public Works
Implementing agency (SPV)
Kochi Metro Rail Limited (KMRL)
Announced under
Trivandrum / Kozhikode Light Metro Project.
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
01-10-2026
First recorded
30-09-2026