Construction of Flyover at Sreekariyam in Thiruvananthapuram
Approved by KIIFB
₹168.68 crore
₹1,68,68,02,675
Paid so far
₹115.01 crore
₹1,15,00,54,336 · 68.2% of the amount approved
Works
5
₹115.01 crore paid across the works
KIIFB's figures do not agree here: its list says ₹1,68,68,02,675 was approved for the project, while the approvals of the works add up to ₹1,76,80,21,654. Both are shown as the source states them.
Works (5)
Land Acquisition for Sreekaryam Flyover
Work awarded
₹98.36 crorepaid
₹98.36 croreapproved
Utility Shifting - Kerala Water Authority
Work awarded
₹4 crorepaid
₹4 croreapproved
Utility Shifting - KSEB
Work awarded
₹2.58 crorepaid
₹2.58 croreapproved
Utility Shifting - BSNL
Work awarded
₹48.38 lakhpaid
₹48.38 lakhapproved
Construction of Flyover at Sreekaryam - Civil Works
Work awarded
₹9.58 crorepaid
₹71.38 croreapproved
Total of the works: ₹1,76,80,21,654 approved, ₹1,15,00,54,336 paid.