Works (8)
Package 1 (Main Building Mattanur Revenue Tower)
Work awarded₹15.4 crorepaid
₹16.03 croreapproved
Its record on the map dashboard · REV001-02-01
Construction of Revenue Tower, Mattanur, Kannur Package II - Electrification
Work started₹52.45 lakhpaid
₹1.21 croreapproved
Its record on the map dashboard · REV001-02-02
Statutory Clearance for Construction of Revenue Tower Mattannur
Work awarded₹2.09 lakhpaid
₹2.09 lakhapproved
Construction of Revenue Tower at Mattannur - Package III - Supply, Installation, Testing & Commissioning of Lifts
Work awarded₹47.55 lakhpaid
₹47.55 lakhapproved
Its record on the map dashboard · REV001-02-04
Construction of Revenue Tower at Mattannur - Package IV - STP
Work awarded₹9.19 lakhpaid
₹26.23 lakhapproved
Its record on the map dashboard · REV001-02-05
Construction of Revenue Tower at Mattanur - Firefighting works
Work awarded₹53.65 lakhpaid
₹72.01 lakhapproved
Its record on the map dashboard · REV001-02-06
SOP to Revenue tower HT DP under Electrical section Mattannur (Reimbursement)
Work awarded₹2.5 lakhpaid
₹2.5 lakhapproved
Construction of Revenue Tower, Mattanur - PCB fees (Reimbursement)
Work awarded₹4.74 lakhpaid
₹4.74 lakhapproved
Total of the works: ₹18,79,29,676 approved, ₹17,11,74,477 paid.