Kanakkuമലയാളം
PowerApproved

220KV GIS Package - I (Aluva, Kaloor, Kunnamangalam and Brahmapuram bays)

Approved by KIIFB

₹224.82 crore

₹2,24,82,00,000

Paid so far

₹164.2 crore

₹1,64,20,26,233 · 73% of the amount approved

Works

1

₹164.2 crore paid across the works

KIIFB's list gives “payment released” for this project as ₹4,92,60,78,699. That is exactly 3 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹1,64,20,26,233.

Works (1)

Details

Department
Power
Implementing agency (SPV)
KSEBL Transgrid
Announced under
Transgrid Project KSEB
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
30-09-2026
First recorded
30-09-2026

The same project on the map dashboard

KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.