Higher EducationApproved

Palakkad Cluster 1 Phase 4

Approved by KIIFB

₹8.26 crore

₹8,26,29,830

Paid so far

₹7.71 crore

₹7,70,58,369 · 93.3% of the amount approved

Works

3

₹7.71 crore paid across the works

KIIFB's list gives “payment released” for this project as ₹15,41,16,738. That is exactly 2 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹7,70,58,369.

Works (3)

Statutory payment for FIRE NOC at Augmentation of Infrastructural Facilities at Government Arts & Science College Thrithala

Work awarded
₹0paid
₹34,740approved

Statutory payment to KSEB & Electrical Inspectorate for obtaining electrical connection at Augmentation of Infrastructural Facilities at Government Arts & Science College Thrithala

Work awarded
₹0paid
₹54,139approved

Total of the works: ₹7,89,07,296 approved, ₹7,70,58,369 paid.

Details

Department
Higher Education
Implementing agency (SPV)
KITCO Ltd
Announced under
Augmentation of Infrastructural Facilities at Government Colleges in Kerala
KIIFB status
Approved
Name as KIIFB publishes it
PALAKKAD CLUSTER 1 PHASE 4

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026

The same project on the map dashboard

KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.