PALAKKAD-KANNUR-KASARGODE CLUSTER-Phase-7

Approved by KIIFB

₹6 crore

₹6,00,00,000

Paid so far

₹4.45 crore

₹4,45,29,914 · 74.2% of the amount approved

Works

2

₹4.45 crore paid across the works

KIIFB's list gives “payment released” for this project as ₹17,81,19,656. That is exactly 4 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹4,45,29,914.

Works (2)

GHSS Maloth Kasba

Work awarded
₹2.27 crorepaid
₹2.27 croreapproved

GHSS MALUR

Work awarded
₹2.19 crorepaid
₹2.3 croreapproved

Total of the works: ₹4,56,73,980 approved, ₹4,45,29,914 paid.

Details

Department
General Education
Implementing agency (SPV)
INKEL Limited
Announced under
Betterment of infrastructure facilities in 229 schools
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026