Kanakkuമലയാളം
Higher EducationApproved

Ernakulam cluster phase 1

Approved by KIIFB

₹6.01 crore

₹6,00,88,302

Paid so far

₹5.3 crore

₹5,30,41,101 · 88.3% of the amount approved

Works

1

₹5.3 crore paid across the works

KIIFB's figures do not agree here: its list says ₹6,00,88,302 was approved for the project, while the approvals of the works add up to ₹7,03,34,354. Both are shown as the source states them.

Works (1)

Details

Department
Higher Education
Implementing agency (SPV)
KITCO Ltd
Announced under
Augmentation of Infrastructural Facilities at Government Colleges in Kerala
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
30-09-2026
First recorded
30-09-2026

The same project on the map dashboard

KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.