Kanakkuമലയാളം
Health & Family WelfareApproved

Development of District Hospital Palakkad

Approved by KIIFB

₹98.89 crore

₹98,89,41,419

Paid so far

₹54.06 crore

₹54,06,07,991 · 54.7% of the amount approved

Works

7

₹54.06 crore paid across the works

Works (7)

Dh Plkd-Fire Noc

Work awarded
₹3.46 lakhpaid
₹3.46 lakhapproved

DH PLKD-Electrical Cable Rerouting

Work awarded
₹14.98 lakhpaid
₹14.98 lakhapproved

DH-PLKD -Rerouting Water Supply Lines

Work awarded
₹3.3 lakhpaid
₹3.7 lakhapproved

DH Palakkad-GRIHA Registration Fees

Work awarded
₹3.54 lakhpaid
₹3.54 lakhapproved

DH Palakkad-Shifting of Power Laundry

Work awarded
₹62,540paid
₹62,540approved

Total of the works: ₹90,67,36,609 approved, ₹54,06,07,991 paid.

Details

Department
Health & Family Welfare
Implementing agency (SPV)
HLL Infra Tech Services Ltd
Announced under
Improvements to the infrastructure of Taluk, District and General Hospitals
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
06-11-2026
Works last checked
06-11-2026
First recorded
30-09-2026

The same project on the map dashboard

KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.

Recorded changes

RetrievedFieldBefore → after
06-11-2026work[Development of District Hospital Palakkad-Physical infrastructure].paid_amount471494162 → 523068805
06-11-2026paid_amount489033348 → 540607991