Kollam Cluster 1
Approved by KIIFB
₹19.71 crore
₹19,70,70,143
Paid so far
₹8.34 crore
₹8,34,11,673 · 42.3% of the amount approved
Works
5
₹8.34 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹41,70,58,365. That is exactly 5 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹8,34,11,673.
Works (5)
₹2.84 crorepaid
₹3.79 croreapproved
Govt HSS Kummil
Work awarded₹1.91 crorepaid
₹4.07 croreapproved
Govt. UPS Kadakkal
Work awarded₹2.17 crorepaid
₹3.69 croreapproved
GHSS Poruvazhi
Work started₹1.42 crorepaid
₹4.09 croreapproved
Govt Girls HSS Thazhava
Work awarded₹0paid
₹3.73 croreapproved
Total of the works: ₹19,37,34,692 approved, ₹8,34,11,673 paid.
Details
- Department
- General Education
- Implementing agency (SPV)
- Kerala Institute of Local Administration (KILA)
- Announced under
- Betterment of Infrastructure facilities in 166 schools
- KIIFB status
- Approved
Source
- Source
- KIIFB project statuskiifb.org/prjStatus.jsp
- Amounts retrieved
- 30-09-2026
- Works last checked
- 02-10-2026
- First recorded
- 30-09-2026
The same project on the map dashboard
KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.
- GVHSS Kulakkada GED006-15-01 · ₹2.1 crore spent
- Govt. UPS Kadakkal GED006-15-03 · ₹1.98 crore spent
- Govt HSS Kummil GED006-15-02 · ₹94.11 lakh spent
- GHSS Poruvazhi GED006-15-04 · ₹71.16 lakh spent
- Govt Girls HSS Thazhava GED006-15-05