Kanakkuമലയാളം
General EducationApproved

Thrissur, Palakkad cluster-Phase 2

Approved by KIIFB

₹17.99 crore

₹17,98,85,000

Paid so far

₹15.74 crore

₹15,73,71,362 · 87.5% of the amount approved

Works

6

₹15.74 crore paid across the works

KIIFB's list gives “payment released” for this project as ₹62,94,85,448. That is exactly 4 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹15,73,71,362.

Works (6)

Total of the works: ₹16,16,39,510 approved, ₹15,73,71,362 paid.

Details

Department
General Education
Announced under
Betterment of infrastructure facilities in 229 schools
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026

The same project on the map dashboard

KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.