Kozhikode-Wayanad Cluster Phase 2
Approved by KIIFB
₹30 crore
₹30,00,00,000
Paid so far
₹26.52 crore
₹26,52,49,355 · 88.4% of the amount approved
Works
6
₹26.52 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹1,32,62,46,775. That is exactly 5 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹26,52,49,355.
Works (6)
₹4.99 crorepaid
₹5 croreapproved
Govt. Higher Secondary School, Kuttiady
Work awarded₹4.24 crorepaid
₹4.3 croreapproved
Valayam Govt. HSS, Kozhikode
Work started₹4.63 crorepaid
₹4.84 croreapproved
Govt HSS, Pannur, Koduvally
Work started₹3.91 crorepaid
₹4.05 croreapproved
Neeleswaram Govt. HSS, Mukkam, Kozhikode
Work started₹3.95 crorepaid
₹3.99 croreapproved
Meenangadi Govt. HSS,Wayanad
Work started₹4.8 crorepaid
₹4.99 croreapproved
Total of the works: ₹27,16,15,408 approved, ₹26,52,49,355 paid.
Details
- Department
- General Education
- Implementing agency (SPV)
- Kerala Infrastructure and Technology for Education (KITE)
- Announced under
- PPE Mission-Upgradation of one school in each constituency
- KIIFB status
- Approved
Source
- Source
- KIIFB project statuskiifb.org/prjStatus.jsp
- Amounts retrieved
- 30-09-2026
- Works last checked
- 02-10-2026
- First recorded
- 30-09-2026
The same project on the map dashboard
KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.
- Govt. Ganapath Vocational Higher Secondary School, Feroke GED005-22-01 · ₹4.77 crore spent
- Meenangadi Govt. HSS,Wayanad GED005-22-06 · ₹4.58 crore spent
- Valayam Govt. HSS, Kozhikode GED005-22-03 · ₹4.42 crore spent
- Govt. Higher Secondary School, Kuttiady GED005-22-02 · ₹4.04 crore spent
- Neeleswaram Govt. HSS, Mukkam, Kozhikode GED005-22-05 · ₹3.77 crore spent
- Govt HSS, Pannur, Koduvally GED005-22-04 · ₹3.73 crore spent