Chittur Govt. B.h.s.s
Work awarded₹5.1 crorepaid
₹5.13 croreapproved
₹10 crore
₹10,00,00,000
₹9.06 crore
₹9,06,00,485 · 90.6% of the amount approved
2
₹9.06 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹18,12,00,970. That is exactly 2 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹9,06,00,485.
Total of the works: ₹9,37,42,919 approved, ₹9,06,00,485 paid.