Infrastructural Development of Arts and Science Colleges - Govt College Attingal
Work awarded₹9.43 crorepaid
₹9.44 croreapproved
₹17.25 crore
₹17,25,00,000
₹14.52 crore
₹14,51,54,336 · 84.1% of the amount approved
2
₹14.52 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹29,03,08,671. That is exactly 2 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹14,51,54,336.
Total of the works: ₹14,93,80,960 approved, ₹14,51,54,336 paid.
KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.