General EducationApproved

Kasaragod Cluster - 24

Approved by KIIFB

₹12.15 crore

₹12,15,14,570

Paid so far

₹9.15 crore

₹9,15,47,649 · 75.3% of the amount approved

Works

13

₹9.15 crore paid across the works

KIIFB's list gives “payment released” for this project as ₹27,46,42,947. That is exactly 3 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹9,15,47,649.

KIIFB's figures do not agree here: its list says ₹12,15,14,570 was approved for the project, while the approvals of the works add up to ₹12,37,54,456. Both are shown as the source states them.

Works (13)

Total of the works: ₹12,37,54,456 approved, ₹9,15,47,649 paid.

Details

Department
General Education
Announced under
Betterment of Infrastructure facilities in 446 schools- 1 Cr category-KILA
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
29-10-2026
Works last checked
29-10-2026
First recorded
30-09-2026

The same project on the map dashboard

KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.

Recorded changes

RetrievedFieldBefore → after
29-10-2026work[GHSS Bekur].paid_amount2409464 → 5358686
29-10-2026paid_amount88598427 → 91547649
15-10-2026work[GHSS Angadimoger].paid_amount0 → 2958319
15-10-2026paid_amount85640108 → 88598427