Alappuzha Phase-3 Cluster 1
Approved by KIIFB
₹6 crore
₹6,00,00,000
Paid so far
₹6.02 crore
₹6,01,79,868
Works
2
₹6.02 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹18,05,39,604. That is exactly 3 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹6,01,79,868.
KIIFB's figures do not agree here: its list says ₹6,00,00,000 was approved for the project, while the approvals of the works add up to ₹6,07,14,396. Both are shown as the source states them.
Works (2)
₹3.11 crorepaid
₹3.15 croreapproved
GHSS, Thirunallur
Work awarded₹2.91 crorepaid
₹2.92 croreapproved
Total of the works: ₹6,07,14,396 approved, ₹6,01,79,868 paid.
Details
- Department
- General Education
- Implementing agency (SPV)
- Kerala Infrastructure and Technology for Education (KITE)
- Announced under
- Betterment of infrastructure facilities in 229 schools
- KIIFB status
- Approved
Source
- Source
- KIIFB project statuskiifb.org/prjStatus.jsp
- Amounts retrieved
- 30-09-2026
- Works last checked
- 02-10-2026
- First recorded
- 30-09-2026
The same project on the map dashboard
KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.
- GHS, Pollathai GED008-43-02 · ₹2.97 crore spent
- GHSS, Thirunallur GED008-43-03 · ₹2.78 crore spent
- GHS, Naluchira GED008-43-01
- GHS, Kakkazhom GED008-43-04