Alappuzha and Idukki - Cluster 8
Approved by KIIFB
₹12.42 crore
₹12,41,90,944
Paid so far
₹7.22 crore
₹7,22,28,144 · 58.2% of the amount approved
Works
11
₹7.22 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹28,89,12,576. That is exactly 4 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹7,22,28,144.
KIIFB's figures do not agree here: its list says ₹12,41,90,944 was approved for the project, while the approvals of the works add up to ₹12,70,01,513. Both are shown as the source states them.
Works (11)
Project -Infrastructure Development of Schools - Construction of Building at Govt. Tribal UP School, Kumily
Work awardedProject: Betterment of Infrastructure facilities in Schools - Construction of Building for GVHSS Nedumkandam
Work awardedProject - Infrastructure Development of Schools - Construction of Building at GHSS Amaravathy, Kumily
Work awardedCL-08 Construction of School building to Govt. KKKPMHSS Ambalapuzha in Ambalappuzha South GP, Alappuzha
Work startedCL-08 Construction of school building to GOVT GHSS Alappuzha in Alappuzha Municipality, Alappuzha
Work awardedProject - Betterment of Infrastructure of schools - Construction of building for Rajakumari GVHSS AND HS in Rajakumari GP
Work awardedGHS Pambanar
Work awardedGUPS Thampakachuvadu
Work awardedGVHSS Mavelikara
Work startedGGHSS Kayamkulam
Work awardedTotal of the works: ₹12,70,01,513 approved, ₹7,22,28,144 paid.
Details
- Department
- General Education
- Implementing agency (SPV)
- Kerala Institute of Local Administration (KILA)
- Announced under
- Betterment of Infrastructure facilities in 446 schools- 1 Cr category-KILA
- KIIFB status
- Approved
Source
- Source
- KIIFB project statuskiifb.org/prjStatus.jsp
- Amounts retrieved
- 30-09-2026
- Works last checked
- 02-10-2026
- First recorded
- 30-09-2026
The same project on the map dashboard
KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.
- GUPS Thampakachuvadu GED003-09-09 · ₹1.34 crore spent
- Project: Betterment of Infrastructure facilities in Schools - Construction of Building for GVHSS Nedumkandam GED003-09-03 · ₹1.02 crore spent
- Project -Infrastructure Development of Schools - Construction of Building at Govt. Tribal UP School, Kumily GED003-09-02 · ₹99.7 lakh spent
- Project - Infrastructure Development of Schools - Construction of Building at GHSS Amaravathy, Kumily GED003-09-04 · ₹94.65 lakh spent
- CL-08 Construction of school building to GOVT GHSS Alappuzha in Alappuzha Municipality, Alappuzha GED003-09-06 · ₹93.17 lakh spent
- Construction of School Building at Govt High School, Anakkara (School code 30038) In Chakkupallam GP, Peerumedu Constituency, Idukki District GED003-09-01 · ₹58.19 lakh spent
- Project - Betterment of Infrastructure of schools - Construction of building for Rajakumari GVHSS AND HS in Rajakumari GP GED003-09-07 · ₹57.6 lakh spent
- CL-08 Construction of School building to Govt. KKKPMHSS Ambalapuzha in Ambalappuzha South GP, Alappuzha GED003-09-05 · ₹47.16 lakh spent
- GHS Pambanar GED003-09-08
- GVHSS Mavelikara GED003-09-10
- GGHSS Kayamkulam GED003-09-11