Govt. Boys VHSS, Peruva
Work awarded₹6.62 crorepaid
₹6.62 croreapproved
₹15 crore
₹15,00,00,000
₹19.63 crore
₹19,62,54,103
3
₹19.63 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹58,87,62,309. That is exactly 3 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹19,62,54,103.
KIIFB's figures do not agree here: its list says ₹15,00,00,000 was approved for the project, while the approvals of the works add up to ₹20,67,53,932. Both are shown as the source states them.
Total of the works: ₹20,67,53,932 approved, ₹19,62,54,103 paid.