Thiruvananthapuram Cluster 2
Approved by KIIFB
₹15.13 crore
₹15,12,58,080
Paid so far
₹10 crore
₹9,99,67,850 · 66.1% of the amount approved
Works
4
₹10 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹29,99,03,550. That is exactly 3 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹9,99,67,850.
KIIFB's figures do not agree here: its list says ₹15,12,58,080 was approved for the project, while the approvals of the works add up to ₹16,23,95,288. Both are shown as the source states them.
Works (4)
GVHSS Pirappancode
Work awardedGVHSS Pakalkuri
Work awardedGHS Koduvazhanoor
Work awardedTotal of the works: ₹16,23,95,288 approved, ₹9,99,67,850 paid.
Details
- Department
- General Education
- Implementing agency (SPV)
- Kerala Institute of Local Administration (KILA)
- Announced under
- Betterment of Infrastructure facilities in 166 schools
- KIIFB status
- Approved
Source
- Source
- KIIFB project statuskiifb.org/prjStatus.jsp
- Amounts retrieved
- 30-09-2026
- Works last checked
- 01-10-2026
- First recorded
- 30-09-2026
The same project on the map dashboard
KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.
- GHSS Ayirooppara GED006-06-01 · ₹3.12 crore spent
- GVHSS Pakalkuri GED006-06-03 · ₹2.3 crore spent
- GVHSS Pirappancode GED006-06-02 · ₹1.59 crore spent
- GHS Koduvazhanoor GED006-06-04 · ₹1.58 crore spent