Thiruvananthapuram Cluster 3
Approved by KIIFB
₹15.68 crore
₹15,68,22,938
Paid so far
₹6.01 crore
₹6,00,89,634 · 38.3% of the amount approved
Works
5
₹6.01 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹24,03,58,536. That is exactly 4 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹6,00,89,634.
Works (5)
₹0paid
₹1approved
GUPS Vithura
Work awarded₹59.49 lakhpaid
₹4.17 croreapproved
GVHSS Paruthipally
Work awarded₹3.35 crorepaid
₹3.66 croreapproved
GHSS Aruvikkara
Work awarded₹2.07 crorepaid
₹3.86 croreapproved
GUPS Kaniyapuram New
Work awarded₹0paid
₹3.9 croreapproved
Total of the works: ₹15,58,12,647 approved, ₹6,00,89,634 paid.
Details
- Department
- General Education
- Implementing agency (SPV)
- Kerala Institute of Local Administration (KILA)
- Announced under
- Betterment of Infrastructure facilities in 166 schools
- KIIFB status
- Approved
Source
- Source
- KIIFB project statuskiifb.org/prjStatus.jsp
- Amounts retrieved
- 30-09-2026
- Works last checked
- 01-10-2026
- First recorded
- 30-09-2026
The same project on the map dashboard
KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.
- GVHSS Paruthipally GED006-18-03 · ₹2.95 crore spent
- GHSS Aruvikkara GED006-18-04 · ₹65.34 lakh spent
- GUPS Vithura GED006-18-02 · ₹30.11 lakh spent
- GUPS Kaniyapuram GED006-18-01
- GUPS Kaniyapuram New GED006-18-05