CHARAMANGALAM GDVHSS
Work awarded₹3.65 crorepaid
₹3.68 croreapproved
₹12 crore
₹12,00,00,000
₹12.23 crore
₹12,23,39,030
5
₹12.23 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹48,93,56,120. That is exactly 4 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹12,23,39,030.
KIIFB's figures do not agree here: its list says ₹12,00,00,000 was approved for the project, while the approvals of the works add up to ₹12,34,93,710. Both are shown as the source states them.
Total of the works: ₹12,34,93,710 approved, ₹12,23,39,030 paid.