Kanakkuമലയാളം
General EducationApproved

Trivandrum & Alappuzha cluster-Phase III

Approved by KIIFB

₹10 crore

₹10,00,00,000

Paid so far

₹10.57 crore

₹10,56,66,390

Works

2

₹10.57 crore paid across the works

KIIFB's figures do not agree here: its list says ₹10,00,00,000 was approved for the project, while the approvals of the works add up to ₹10,75,73,115. Both are shown as the source states them.

Works (2)

GHSS Nedumangad

Work started
₹4.76 crorepaid
₹4.77 croreapproved

GVHSS Mulakuzha

Work awarded
₹5.81 crorepaid
₹5.99 croreapproved

Total of the works: ₹10,75,73,115 approved, ₹10,56,66,390 paid.

Details

Department
General Education
Announced under
PPE Mission-Upgradation of one school in each constituency
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
01-10-2026
First recorded
30-09-2026