Thalasseri heritage project - Phase III- Development of Overbury's Bridge /plaza to view the historical Thalasseri Sea pier

Approved by KIIFB

₹36.28 crore

₹36,27,59,986

Paid so far

₹10 lakh

₹10,00,000 · 0.3% of the amount approved

Works

1

₹10 lakh paid across the works

Works (1)

Thalasseri heritage project - Phase III- Development of Overbury's Bridge /plaza to view the historical Thalasseri Sea pier-CRZ

Work awarded
₹10 lakhpaid
₹10 lakhapproved

Details

Department
Tourism
Announced under
Thalassery Heritage Project
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026