Shore protection works and providing beach landing facility in Poonthura- Modelstudy
Work awarded₹42.07 lakhpaid
₹42.07 lakhapproved
₹20.78 crore
₹20,78,10,743
₹10.53 crore
₹10,52,74,375 · 50.7% of the amount approved
4
₹10.53 crore paid across the works
Total of the works: ₹20,76,21,473 approved, ₹10,52,74,375 paid.
KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.