Construction of 10 bedded isolation wards in 140 LAC
Approved by KIIFB
₹236.3 crore
₹2,36,30,38,160
Paid so far
₹113.12 crore
₹1,13,11,82,901 · 47.9% of the amount approved
Works
37
₹113.12 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹15,83,65,60,614. That is exactly 14 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹1,13,11,82,901.
Works (37)
Isolation wards in Hospitals in 140 LAC in the State
Work awarded
₹98.73 crorepaid
₹118.49 croreapproved
Centralised Medical Gas Supply for 90 isolation wards
Work awarded
₹7.31 crorepaid
₹12.65 croreapproved
Procurement of Fowlers Cot & Iron Cot
Work awarded
₹2.2 crorepaid
₹2.71 croreapproved
Procurement of Pigeon hole locker cupboard (12 locker )
Work awarded
₹0paid
₹18 lakhapproved
Procurement of Crash cart for Isolation wards
Work awarded
₹8.02 lakhpaid
₹40.14 lakhapproved
Procurement of Defibrillator with Cardiac Monitor for Isolation ward
Work awarded
₹47.98 lakhpaid
₹1.54 croreapproved
Procurement of Dressing trolley & Patient Trolley for isolation wards
Work awarded
₹7.27 lakhpaid
₹37.31 lakhapproved
Procurement of ECG machine single channel for Isolation wards
Work awarded
₹0paid
₹25.1 lakhapproved
Procurement of Instrument Trolley with two shelves
Work awarded
₹4.36 lakhpaid
₹9.13 lakhapproved
Procurement of Suction Apparatus for Isolation wards
Work started
₹0paid
₹26.61 lakhapproved
Procurement of Refrigerator Model B for isolation wards
Work awarded
₹22.15 lakhpaid
₹23.22 lakhapproved
Procurement of Multiparameter Monitors for Isolation ward
Work awarded
₹1.95 crorepaid
₹5.27 croreapproved
Procurement of Bedside locker for isolation wards
Work started
₹19.97 lakhpaid
₹49.91 lakhapproved
Procurement of IV stand for isolation stand
Work awarded
₹0paid
₹19.65 lakhapproved
Procurement of BP Apparatus & Weighing machine for isolation wards
Work started
₹0paid
₹10.85 lakhapproved
Procurement of Vertical Autoclave for Isolation wards
Work awarded
₹91.74 lakhpaid
₹1 croreapproved
Procurement of Wheel Chair Foldable Type for Isolation Wards
Work awarded
₹0paid
₹11.33 lakhapproved
Procurement of Mobile Spot Light LED Model B for Isolation Wards
Work awarded
₹6.01 lakhpaid
₹14.62 lakhapproved
Procurement of X-Ray Lobby LED Double Film for Isolation Wards
Work awarded
₹22 lakhpaid
₹39.59 lakhapproved
Procurement of Nebuliser for Isolation Wards
Work started
₹2.1 lakhpaid
₹3.78 lakhapproved
Procurement of Examination Table - Examination Cot for Isolation Wards
Work awarded
₹0paid
₹20.07 lakhapproved
Procurement of Table for Isolation Wards
Work awarded
₹7.59 lakhpaid
₹12.26 lakhapproved
Procurement of Executive Chair with Arm Rest for Isolation Wards
Work awarded
₹0paid
₹5.05 lakhapproved
Procurement of Infusion Pump for Isolation Wards
Work awarded
₹6.12 lakhpaid
₹19.66 lakhapproved
Procuremnent of Over Bed Table for Isolation Wards
Work awarded
₹2.03 lakhpaid
₹61.6 lakhapproved
Procurement of Pulse Oxymeter for Isolation Wards
Work awarded
₹37,580paid
₹8.46 lakhapproved
Procurement of Almarah Steel for Isolation Wards
Work awarded
₹43.98 lakhpaid
₹46.04 lakhapproved
Procurement of Syringe Pump for Isolation Wards
Work awarded
₹0paid
₹15.75 lakhapproved
Procurement of Stethescope for Isolation wards
Work started
₹1.14 lakhpaid
₹1.66 lakhapproved
Procurement of Permanent Electric Connections (Transformer Installation cost) for Isolation Wards-Phase
Work awarded
₹0paid
₹42.22 lakhapproved
Procurement of Permanent Electric Connections (Statutory connection fee, Caution Deposit etc) for Isolation Wards
Work awarded
₹0paid
₹26.44 lakhapproved
Supply of Waiting Chair (3 Seater) & Non Revolving Chair.
Work awarded
₹0paid
₹64.78 lakhapproved
Phase 1-Additional Electrification Works for Isolation Wards
Work awarded
₹0paid
₹3.89 lakhapproved
Construction of Isolation Ward-Balance work in 28 Locations-Supply & Installation of False Ceiling Works( Zone 1,2 & 3 )
Work awarded
₹0paid
₹1.84 croreapproved
Construction of Isolation Ward-Balance work in 28 Locations-Supply & Installation of EPS wall & AAC Blocks Works( Zone 1,2 & 3 )
Work awarded
₹0paid
₹1.48 croreapproved
Construction of Isolation Ward-Balance work in 28 Locations-Supply & Installation of Wall and Floor tiles Works( Zone 1,2 & 3 )
Work awarded
₹0paid
₹3.35 croreapproved
Construction of Isolation Ward-Balance work in 28 Locations-Pre Engineering Structure & Roof Sheet Works( Zone 1,2 & 3 )
Work awarded
₹0paid
₹78.34 lakhapproved
Total of the works: ₹1,55,68,61,534 approved, ₹1,13,11,82,901 paid.