Kanakkuമലയാളം
Water ResourcesApproved

WSS to Mattannur and Iritty Municipalities

Approved by KIIFB

₹76.6 crore

₹76,60,00,000

Paid so far

₹70.65 crore

₹70,64,51,052 · 92.2% of the amount approved

Works

7

₹70.65 crore paid across the works

KIIFB's list gives “payment released” for this project as ₹1,41,29,02,104. That is exactly 2 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹70,64,51,052.

Works (7)

WSS to Mattanur and Iritty Municipalities - Package IV -A

Work awarded
₹17.21 lakhpaid
₹28 lakhapproved

KSEB Power Connection

Work awarded
₹18.29 lakhpaid
₹60 lakhapproved

Road Reformation for Ksrrda

Work awarded
₹1.71 crorepaid
₹1.71 croreapproved

Total of the works: ₹72,90,40,349 approved, ₹70,64,51,052 paid.

Details

Department
Water Resources
Implementing agency (SPV)
Kerala Water Authority (KWA)
Announced under
WSS in 10 Municipalities,
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026

The same project on the map dashboard

KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.