Kanakkuമലയാളം
Water ResourcesApproved

Construction of Regulator Cum Bridge across Chittur Puzha at Vadakarappally Palthulli Grama Panchayath in Palakkad District

Approved by KIIFB

₹21.4 crore

₹21,40,47,641

Paid so far

₹20.17 crore

₹20,16,95,594 · 94.2% of the amount approved

Works

1

₹20.17 crore paid across the works

Works (1)

Construction of Regulator Cum Bridge across Chittur Puzha at Vadakarappally Palthulli Grama Panchayath in Palakkad District

Work awarded
₹20.17 crorepaid
₹21.21 croreapproved

Details

Department
Water Resources
Announced under
Construction of Regulator cum Bridge
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026