Water ResourcesApproved

Augmentation of WSS to Karumallur and Kunnukara Panchayaths

Approved by KIIFB

₹48.53 crore

₹48,52,79,650

Paid so far

₹3.08 crore

₹3,08,10,105 · 6.3% of the amount approved

Works

5

₹3.08 crore paid across the works

KIIFB's figures do not agree here: its list says ₹48,52,79,650 was approved for the project, while the approvals of the works add up to ₹61,58,10,500. Both are shown as the source states them.

Works (5)

Augmentation of WSS to Karumallur and Kunnunnikkara

Work awarded
₹10.14 lakhpaid
₹10.14 lakhapproved

Augmentation of WSS to Karumallur and Kunnukara - Land acqusition

Work awarded
₹2.98 crorepaid
₹2.98 croreapproved

Augmentation of WSS to karumaloor and kunnukara panchayaths-Augmentation of WSS to Karumallur and kunnukara panchayaths-phase 1-package 1 -construction ofwell cum pump house-general civil work.

Work awarded
₹0paid
₹15.73 croreapproved

Its record on the map dashboard · WRD025-16-03

Augmentation of WSS to Karumalloor and Kunnukara Panchayaths- Augmentation of WSS to Karumallur and Kunnukara Panchayaths - Phase 1- Package 2 - Construction of 20 MLD WTP and allied works at Malayikkunnu in Kunnukara Panchayath, OHSR of Capacity 8.50LL at Malayikkunnu WTP Compound and Supply & erection of Pump sets.-General Civil Work

Work started
₹0paid
₹26.1 croreapproved

Its record on the map dashboard · WRD025-16-04

Augmentation of WSS to Karumallur and Kunnukara Panchayaths - Phase 1 - Package 3 - Supplying, laying, charging and commissioning of 250 mm DI K9 Clear Water Pumping main towards existing OHSR at UC college and towards proposed OHSR at Manjali in Karumalloor GP, Construction of 10.50 LL capacity OHSR at Manjali in Karumalloor GP-General Civil Work

Work awarded
₹0paid
₹16.67 croreapproved

Its record on the map dashboard · WRD025-16-05

Total of the works: ₹61,58,10,500 approved, ₹3,08,10,105 paid.

Details

Department
Water Resources
Implementing agency (SPV)
Kerala Water Authority (KWA)
Announced under
KIIFB 2017-18 water supply projects
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
30-09-2026
First recorded
30-09-2026

The same project on the map dashboard

KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.