Water ResourcesApproved

Kizhakkanmala Drinking Water Supply Project

Approved by KIIFB

₹53.78 crore

₹53,78,19,571

Paid so far

₹48.71 crore

₹48,71,48,324 · 90.6% of the amount approved

Works

5

₹48.71 crore paid across the works

KIIFB's list gives “payment released” for this project as ₹97,42,96,648. That is exactly 2 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹48,71,48,324.

Works (5)

KSEB Charges for shifting Moonnattumukku Transformer as Part of Kizhakkanmala Drinking Water Supply Project

Work awarded
₹4.95 lakhpaid
₹4.95 lakhapproved

KSEB Charges for Power Allocation in Kizhakkanmala WTP

Work awarded
₹11.42 lakhpaid
₹12.28 lakhapproved

KSEB Charges for Power Allocation in Moonattumukk pump house

Work awarded
₹2.42 lakhpaid
₹2.42 lakhapproved

Total of the works: ₹53,37,90,948 approved, ₹48,71,48,324 paid.

Details

Department
Water Resources
Implementing agency (SPV)
Kerala Water Authority (KWA)
Announced under
KIIFB 2017-18 water supply projects
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
01-10-2026
First recorded
30-09-2026

The same project on the map dashboard

KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.