WSS to Koyilandy & adjoining Panchayaths
Approved by KIIFB
₹85 crore
₹85,00,00,000
Paid so far
₹77.11 crore
₹77,10,76,597 · 90.7% of the amount approved
Works
9
₹77.11 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹2,31,32,29,791. That is exactly 3 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹77,10,76,597.
Works (9)
₹32.53 crorepaid
₹35.78 croreapproved
WSS to Koyilandy and & adjoining Panchayaths - Package 2
Work awarded₹24.39 crorepaid
₹26.36 croreapproved
WSS to Koyilandy and Adjoining Panchayath Package 3
Work started₹11.01 crorepaid
₹11.11 croreapproved
Govt Payments for pkg 3 of WSS to Koyilandy municipality-Payment to Kuttiady irrigation Dept
Work awarded₹1.14 crorepaid
₹1.14 croreapproved
Govt.Payment for Package 2 of WSS to Koyilandy Muncipality &Adj.Panchayaths
Work awarded₹1.71 crorepaid
₹1.71 croreapproved
WSS To Koyilandy and Adjoining Pt.Road Reformation Charge To PWD
Work awarded₹10.06 lakhpaid
₹10.06 lakhapproved
2016-17?SIP:WSS to Koyilandy Muncipality and Adjoining Panchayaths (Phase I): Package 4
Work awarded₹5.13 crorepaid
₹5.2 croreapproved
2016-17?SIP:WSS to Koyilandy Muncipality and Adjoining Panchayaths (Phase I)- GOVT.Payment under package2-Payment to KSEB for power connection
Work awarded₹4.68 lakhpaid
₹4.72 lakhapproved
WSS To Koyilandy and adjoining panchayath(Phase1)-Package3-Road restoration
Work awarded₹1.05 crorepaid
₹1.05 croreapproved
Total of the works: ₹82,49,01,222 approved, ₹77,10,76,597 paid.
Details
- Department
- Water Resources
- Implementing agency (SPV)
- Kerala Water Authority (KWA)
- Announced under
- WSS in 10 Municipalities,
- KIIFB status
- Approved
Source
- Source
- KIIFB project statuskiifb.org/prjStatus.jsp
- Amounts retrieved
- 30-09-2026
- Works last checked
- 02-10-2026
- First recorded
- 30-09-2026
The same project on the map dashboard
KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.
- WSS to Koyilandy and Adjoining Panchayath Package 1 WRD002-07-01 · ₹31.13 crore spent
- WSS to Koyilandy and & adjoining Panchayaths - Package 2 WRD002-07-02 · ₹23.26 crore spent
- WSS to Koyilandy and Adjoining Panchayath Package 3 WRD002-07-03 · ₹10.42 crore spent
- 2016-17–SIP:WSS to Koyilandy Muncipality and Adjoining Panchayaths (Phase I): Package 4 WRD002-07-07 · ₹4.89 crore spent
- WSS To Koyilandy and adjoining panchayath(Phase1)-Package3-Road restoration WRD002-07-10 · ₹1.01 crore spent
- SIP-WSS To Koyilandy Muncipality and adjoining Panchayath(Phase1)-Package3 _road restoration WRD002-07-11