Kanakkuമലയാളം
Water ResourcesApproved

WSS to Ala, Puliyoor, Budhanoor, Pandanad, by including Mulakkuzha, Venmony Panchayaths and Chengannur Municipality in Alappuzha District

Approved by KIIFB

₹244.08 crore

₹2,44,07,98,930

Paid so far

₹99.59 crore

₹99,58,68,462 · 40.8% of the amount approved

Works

6

₹99.59 crore paid across the works

Works (6)

WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths & Chengannur Municipality in Alappuzha Disctrict? Package I?Construction of 36 MLD W T P, Renovation to existing Intake well cum Pump house -, Transformer room, RWPM , S/L of Distribution lines, transformer, Pumpset etc .

Work awarded
₹32.57 crorepaid
₹32.93 croreapproved

WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths & Chengannur Municipality in Alappuzha District- Package-II

Work awarded
₹6.63 crorepaid
₹71.28 croreapproved

WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths & Chengannur Municipality in Alappuzha District- Package-V

Work awarded
₹3.97 crorepaid
₹4.03 croreapproved

Railway Push through works

Work awarded
₹22.54 lakhpaid
₹22.54 lakhapproved

WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayat and Chengannur Muncipality in ALP District -Package 1-Demand notice for power connection to Kolamukkam pumphouse with dedicated feeder under Electrical section Chengannur, Demand notice for power connection to WTP with dedicated feeder under Electrical section Mulakkuzha.

Work awarded
₹1.62 crorepaid
₹1.62 croreapproved

WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths & Chengannur Municipality-Package 3-General Civil Work

Work awarded
₹54.57 crorepaid
₹112.27 croreapproved

Total of the works: ₹2,22,35,99,928 approved, ₹99,58,68,462 paid.

Details

Department
Water Resources
Implementing agency (SPV)
Kerala Water Authority (KWA)
Announced under
KIIFB 2017-18 water supply projects
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026