Malappuram Phase-3 Cluster 2
Approved by KIIFB
₹14.56 crore
₹14,56,00,000
Paid so far
₹13.7 crore
₹13,70,32,379 · 94.1% of the amount approved
Works
5
₹13.7 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹27,40,64,758. That is exactly 2 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹13,70,32,379.
Works (5)
₹2.38 crorepaid
₹2.52 croreapproved
Government High School, Chaliyapuram
Work awarded₹2.67 crorepaid
₹2.77 croreapproved
GHSS, Kottappuram
Work started₹3 crorepaid
₹3.02 croreapproved
GHSS, Karakunnu
Work awarded₹2.93 crorepaid
₹2.93 croreapproved
GVHSS, nellikoth
Work awarded₹2.73 crorepaid
₹2.74 croreapproved
Total of the works: ₹13,98,52,674 approved, ₹13,70,32,379 paid.
Details
- Department
- General Education
- Implementing agency (SPV)
- WAPCOS Limited
- Announced under
- Betterment of infrastructure facilities in 229 schools
- KIIFB status
- Approved
Source
- Source
- KIIFB project statuskiifb.org/prjStatus.jsp
- Amounts retrieved
- 30-09-2026
- Works last checked
- 02-10-2026
- First recorded
- 30-09-2026
The same project on the map dashboard
KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.
- GHSS, Kottappuram GED008-57-03 · ₹2.86 crore spent
- GHSS, Karakunnu GED008-57-04 · ₹2.8 crore spent
- GVHSS, nellikoth GED008-57-05 · ₹2.61 crore spent
- Government High School, Chaliyapuram GED008-57-02 · ₹2.57 crore spent
- Vazhakkad GHSS GED008-57-01 · ₹2.3 crore spent