Thalassery- Kuthuparamba Comprehensive Drinking Water Project -Package I
Work awarded₹17.89 crorepaid
₹78.49 croreapproved
₹85.86 crore
₹85,86,01,000
₹18.41 crore
₹18,40,55,803 · 21.4% of the amount approved
2
₹18.41 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹36,81,11,606. That is exactly 2 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹18,40,55,803.
Total of the works: ₹81,26,75,045 approved, ₹18,40,55,803 paid.