Kanakkuമലയാളം
Scheduled Caste DevelopmentApproved

Construction of MRS at Thonnakkal, Thiruvananthapuram

Approved by KIIFB

₹16.96 crore

₹16,95,64,900

Paid so far

₹13.91 crore

₹13,91,21,294 · 82% of the amount approved

Works

3

₹13.91 crore paid across the works

Works (3)

Total of the works: ₹13,98,92,697 approved, ₹13,91,21,294 paid.

Details

Department
Scheduled Caste Development
Announced under
Modernisation of all Pre metric and Post metric Hostel in Kerala
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
01-10-2026
First recorded
30-09-2026

The same project on the map dashboard

KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.