Treated Drinking Water Project including Kottukal and Athiyannur Panchayats - Phase 1
Work started₹25.54 crorepaid
₹26.37 croreapproved
₹26.73 crore
₹26,73,33,321
₹25.87 crore
₹25,86,59,229 · 96.8% of the amount approved
3
₹25.87 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹51,73,18,458. That is exactly 2 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹25,86,59,229.
Total of the works: ₹26,69,99,320 approved, ₹25,86,59,229 paid.