Rehabilitation & Resettlement parcel for WCC project
Approved by KIIFB
₹209.2 crore
₹2,09,20,00,000
Paid so far
₹2.22 crore
₹2,21,98,012 · 1.1% of the amount approved
Works
7
₹2.22 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹15,53,86,084. That is exactly 7 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹2,21,98,012.
Works (7)
Cost for constituting PMU by the Fisheries Department
Work awarded
₹0paid
₹3.08 croreapproved
Rehabilitation of 36 families in the Varkala region
Work awarded
₹2.22 crorepaid
₹2.22 croreapproved
Rehabilitation of families in Varkala area
Work awarded
₹0paid
₹40.8 croreapproved
Rehabilitation of families in Kadinamkulam area
Work awarded
₹0paid
₹32.32 croreapproved
First and Second instalment of compensation for the rehabilitation of 62 families in Varkala and 6 families Kadinamkulam
Work awarded
₹0paid
₹7.48 croreapproved
Rehabilitation of families and compensation for shops in Trivandrum corporation area
Work awarded
₹0paid
₹118.3 croreapproved
Cost for the valuation of buildings
Work awarded
₹0paid
₹28.22 lakhapproved
Total of the works: ₹2,04,47,97,249 approved, ₹2,21,98,012 paid.