Development of Mahe - Valapattanam stretch of West Coast Canal - Land Acquisition and Rehabilitation
Approved by KIIFB
₹650.5 crore
₹6,50,50,00,000
Paid so far
₹1.12 crore
₹1,12,39,000 · 0.2% of the amount approved
Works
3
₹1.12 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹4,49,56,000. That is exactly 4 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹1,12,39,000.