Construction of Koolimadu Bridge across Chaliyar river in Kozhikode District - Contract work
Work awarded₹16.26 crorepaid
₹16.41 croreapproved
₹21.5 crore
₹21,50,00,000
₹17.58 crore
₹17,58,40,504 · 81.8% of the amount approved
4
₹17.58 crore paid across the works
Total of the works: ₹19,72,69,622 approved, ₹17,58,40,504 paid.