Widening and Improvement of Ottapalam - Perinthalmanna Road CH 11/000 to 16/850 -Contract work
Work awarded₹14.64 crorepaid
₹21.8 croreapproved
₹33.99 crore
₹33,99,07,824
₹17.19 crore
₹17,19,33,913 · 50.6% of the amount approved
3
₹17.19 crore paid across the works
Total of the works: ₹24,35,00,620 approved, ₹17,19,33,913 paid.