Palode Brimore Road - Contract work
Work started₹43.32 crorepaid
₹44.93 croreapproved
₹49.69 crore
₹49,69,00,000
₹44.49 crore
₹44,49,26,808 · 89.5% of the amount approved
3
₹44.49 crore paid across the works
Total of the works: ₹46,09,87,961 approved, ₹44,49,26,808 paid.