Improvements to Valankara Ayroor road Km 0/000 to 8/300
Approved by KIIFB
₹24.09 crore
₹24,08,53,729
Paid so far
₹15.39 crore
₹15,38,79,392 · 63.9% of the amount approved
Works
4
₹15.39 crore paid across the works
Works (4)
Valankara Ayroor road - Contract work
Work awarded
₹15.11 crorepaid
₹15.2 croreapproved
Improvements to Valankara Ayroor road Km 0/000 to 8/300 - shifting utilities by KSEB
Work awarded
₹27.98 lakhpaid
₹41.18 lakhapproved
Improvements to Valankara Ayroor road Km 0/000 to 8/300- KWA utility shifting and removing deep well hand pumps in borewell ,filling borewell and protecting with PCC by GWD
Work awarded
₹0paid
₹42.24 lakhapproved
Improvements to Valankara Ayroor road Km 0/000 to 8/300 in Pathanamthitta District - Balance Work
Work awarded
₹0paid
₹5.05 croreapproved
Total of the works: ₹21,08,98,374 approved, ₹15,38,79,392 paid.