Kanakkuമലയാളം
Public WorksApproved

Improvements to the Hill high way road From Nandarapadvu to Chevar at KM 0/000 to 23/000 in Kasaragod District

Approved by KIIFB

₹54.76 crore

₹54,76,00,000

Paid so far

₹53.52 crore

₹53,52,08,446 · 97.7% of the amount approved

Works

2

₹53.52 crore paid across the works

Works (2)

Hill high way from Nandarapadvu to Chevar in Kasaragod District - Contract work

Work awarded
₹52.94 crorepaid
₹53.85 croreapproved

Improvements to the Hill high way road from Nandarapadvu to Chevar in Kasaragod District - Utility shifting by KSEB

Work started
₹57.7 lakhpaid
₹57.7 lakhapproved

Total of the works: ₹54,42,99,287 approved, ₹53,52,08,446 paid.

Details

Department
Public Works
Implementing agency (SPV)
Kerala Road Fund Board (KRFB)
Announced under
Hill Highway
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026