Kanakkuമലയാളം
Public WorksApproved

2017-18-Hill highway-Improvements to Hill Highway from Vallithod to Ambayathod between Km 36/506 to 45/000,58/450 to 60/480 and 64/700 to 90/000 in Kannur District

Approved by KIIFB

₹83.17 crore

₹83,16,89,762

Paid so far

₹107.08 crore

₹1,07,07,60,358

Works

0

KIIFB lists no works under this project.

Details

Department
Public Works
Implementing agency (SPV)
Kerala Road Fund Board (KRFB)
KIIFB status
Approved
Name as KIIFB publishes it
KIIFB 2017-18-Hill highway-Improvements to Hill Highway from Vallithod to Ambayathod between Km 36/506 to 45/000,58/450 to 60/480 and 64/700 to 90/000 in Kannur District

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
First recorded