Public WorksApproved

Four Laning of NH-4766 - Karamana Kaliyikkavila - Phase-I - Reach II - Pravachambalam to Vazhimukku

Approved by KIIFB

₹162.46 crore

₹1,62,46,00,000

Paid so far

₹99.98 crore

₹99,97,72,046 · 61.5% of the amount approved

Works

5

₹99.98 crore paid across the works

KIIFB's list gives “payment released” for this project as ₹1,99,95,44,092. That is exactly 2 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹99,97,72,046.

Works (5)

Four laning of Karamana Kaliyikkavila Road - Phase I - Reach II - Pravachambalam to Vazhimukku - Contract work

Work awarded
₹90.45 crorepaid
₹95.22 croreapproved

Four Laning of NH-47(66)-Karamana Kaliyikkavila - Phase-I - Reach II - Pravachambalam to Vazhimukku - Utility shifting by KWA

Work awarded
₹2.54 crorepaid
₹2.54 croreapproved

Four Laning of NH-4766-Karamana Kaliyikkavila - Phase-I - Reach II - Pravachambalam to Vazhimukku - Utility shifting by KSEB

Work awarded
₹1.92 crorepaid
₹1.92 croreapproved

Four Laning of NH-4766-Karamana Kaliyikkavila - Phase-I - Reach II - Pravachambalam to Vazhimukku - Utility shifting by Bsnl

Work awarded
₹4.46 crorepaid
₹4.46 croreapproved

FOUR LANING OF NH-4766-KARAMANA KALIYIKKAVILA - PHASE-I - REACH II - PRAVACHAMBALAM TO VAZHIMUKKU - Installation and supply of traffic signals

Work awarded
₹61.34 lakhpaid
₹61.34 lakhapproved

Total of the works: ₹1,04,75,41,388 approved, ₹99,97,72,046 paid.

Details

Department
Public Works
Implementing agency (SPV)
Kerala Road Fund Board (KRFB)
Announced under
137 Roads
KIIFB status
Approved
Name as KIIFB publishes it
FOUR LANING OF NH-4766 - KARAMANA KALIYIKKAVILA - PHASE-I - REACH II - PRAVACHAMBALAM TO VAZHIMUKKU

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026