Kannur Airport connectivity package roads - Upgradation of Chorukkala Bavuparamba Nanicherikkadavu Chekkiyattukavu Mayyil Kololam Road

Approved by KIIFB

₹306.5 crore

₹3,06,49,56,651

Paid so far

₹74.73 crore

₹74,73,06,639 · 24.4% of the amount approved

Works

2

₹74.73 crore paid across the works

KIIFB's list gives “payment released” for this project as ₹1,49,46,13,279. That is exactly 2 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹74,73,06,639.

Works (2)

Upgradation of Chorukkala Bavuparamba Nanicherikkadavu Chekkiyattukavu Mayyil Kololam Road- LA

Work awarded
₹74.73 crorepaid
₹79.3 croreapproved

PackageUpgradation of Chorukkala Bavuparamba Nanicherikkadavu Chekkiyattukavu Mayyil Kololam Road- Contract

Work awarded
₹0paid
₹188.52 croreapproved

Total of the works: ₹2,67,81,89,753 approved, ₹74,73,06,639 paid.

Details

Department
Public Works
Implementing agency (SPV)
Kerala Road Fund Board (KRFB)
Announced under
137 Roads
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026