Public WorksApproved

Improvements and Providing DBM & BC to Kankol - Cheemeni Road Km 0/000 to 10/135 in Kannur District

Approved by KIIFB

₹20.26 crore

₹20,26,00,000

Paid so far

₹22.33 crore

₹22,33,19,916

Works

2

₹22.33 crore paid across the works

KIIFB's figures do not agree here: its list says ₹20,26,00,000 was approved for the project, while the approvals of the works add up to ₹22,46,89,656. Both are shown as the source states them.

Works (2)

Kankol-Cheemeni Road Km 0/000 to 10/135- Contract work

Work awarded
₹20.76 crorepaid
₹20.89 croreapproved

-Improvements to Kankol Cheemeni Road in Kannur District - utility shifting by KSEB

Work awarded
₹1.58 crorepaid
₹1.58 croreapproved

Total of the works: ₹22,46,89,656 approved, ₹22,33,19,916 paid.

Details

Department
Public Works
Implementing agency (SPV)
Kerala Road Fund Board (KRFB)
Announced under
137 Roads
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026