Public WorksApproved

Improvements of Hill Highway from Kollayil Challimukku - Palode, Vithura Iruthalamoola, Aryanad - Kallikkadu Total length 21.080Km in Thiruvananthapuram District

Approved by KIIFB

₹54.71 crore

₹54,71,00,000

Paid so far

₹52.69 crore

₹52,69,26,945 · 96.3% of the amount approved

Works

3

₹52.69 crore paid across the works

KIIFB's list gives “payment released” for this project as ₹1,58,07,80,835. That is exactly 3 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹52,69,26,945.

Works (3)

Hill Highway - Kollayil Challimukku Palode Vithura Iruthalamoola Aryanad Kallikkadu in Thiruvananthapuram District - Contract work

Work started
₹48.74 crorepaid
₹49.26 croreapproved

Improvements of Hill Highway from Kollayil Challimukku - Palode, Vithura Iruthalamoola, Aryanad - Kallikkadu Total length 21.080Km in Thiruvananthapuram District - shifting utilities by KSEB

Work awarded
₹1.68 crorepaid
₹1.68 croreapproved

Improvements of Hill Highway from Kollayil Challimukku - Palode, Vithura Iruthalamoola, Aryanad - Kallikkadu Total length 21.080Km in Thiruvananthapuram District - shifting utilities by KWA

Work awarded
₹2.27 crorepaid
₹2.39 croreapproved

Total of the works: ₹53,33,20,353 approved, ₹52,69,26,945 paid.

Details

Department
Public Works
Implementing agency (SPV)
Kerala Road Fund Board (KRFB)
Announced under
Hill Highway
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026