Kanakkuമലയാളം
Public WorksApproved

Project - Upgradation of Punalur Town Roads

Approved by KIIFB

₹15.15 crore

₹15,15,00,000

Paid so far

₹11.51 crore

₹11,51,27,385 · 76% of the amount approved

Works

2

₹11.51 crore paid across the works

Works (2)

PUNALUR TOWN ROADS - Contract work

Work awarded
₹11.19 crorepaid
₹13.29 croreapproved

Project- Upgradation of Punalur Town Roads - Utility shifting by KSEB

Work awarded
₹32.02 lakhpaid
₹32.02 lakhapproved

Total of the works: ₹13,60,95,585 approved, ₹11,51,27,385 paid.

Details

Department
Public Works
Implementing agency (SPV)
Kerala Road Fund Board (KRFB)
Announced under
137 Roads
KIIFB status
Approved
Name as KIIFB publishes it
KIIFB PROJECT - UPGRADATION OF PUNALUR TOWN ROADS

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026