Construction of Karma Bridges Across Canoli Canal Connecting with Ponnani Port and Chamravattom Regulator in Malappuram District
Approved by KIIFB
₹41.21 crore
₹41,21,05,727
Paid so far
₹36.87 crore
₹36,86,84,620 · 89.5% of the amount approved
Works
3
₹36.87 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹73,73,69,240. That is exactly 2 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹36,86,84,620.
Works (3)
Construction of Karma Bridges Across Canoli Canal Connecting with Ponnani Port and Chamravattom Regulator in Malappuram District - Contract
Work started
₹36.3 crorepaid
₹40.64 croreapproved
Construction of Karma Bridges Across Canoli Canal Connecting with Ponnani Port and Chamravattom Regulator in Malappuram District - Electrification of bridge and approach road by Keltron
Work awarded
₹56.02 lakhpaid
₹56.02 lakhapproved
Construction of Karma Bridges Across Canoli Canal Connecting with Ponnani Port and Chamravattom Regulator in Malappuram District - Shifting utilities by KSEB
Work awarded
₹50,552paid
₹50,552approved
Total of the works: ₹41,20,80,964 approved, ₹36,86,84,620 paid.