Coastal Highway - Construction of Kunjalimarakkar Bridge sandbanks to Kottakkalkadvu in Kozhikode District
Approved by KIIFB
₹65.79 crore
₹65,78,60,000
Paid so far
₹1.45 crore
₹1,44,50,113 · 2.2% of the amount approved
Works
2
₹1.45 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹2,89,00,226. That is exactly 2 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹1,44,50,113.
Works (2)
Coastal Highway - Construction of Kunjalimarakkar Bridge sandbanks to Kottakkalkadvu in Kozhikode District-Land Acquisition
Work awarded
₹1.35 crorepaid
₹2.1 croreapproved
Coastal Highway - Construction of Kunjalimarakkar Bridge sandbanks to Kottakkalkadvu in Kozhikode District - CRZ Clearance
Work awarded
₹10 lakhpaid
₹10 lakhapproved
Total of the works: ₹2,20,35,000 approved, ₹1,44,50,113 paid.